£2.1m
Vital Energi
District Heating
Through 2012 CPC Civils would work with Vital Energi.
Our teams would undertake works to install another 2500m of buried heating mains, water main and gas mains.
This would form a key part of the infrastructure for the new cluster 2/4 at Heslington Campus, York.
Additionally, our team would install LV, HV and comms ducts and cables as well as around 250 No draw pits.
Also, they would install three new HV electrical substations around the campus.
In addition for the York University District Heating project, our teams would install new foul drainage from the cluster and the new Yorkshire sports village complex. This would be at an average depth of 4m in very challenging ground conditions with dewatering wells pointing being required for the majority to cope with the running sand.