2025 © CPC Civils Ltd. All rights reserved.
Design by eSterling
£2,000,000
Kier
Waterway Engineering
Cooper Bridge Weir is located at Cooper Bridge Junction where the Huddersfield Broad canal joins the Calder and Hebble Navigation from the south.
The function of the weir is to maintain upstream water levels of the Calder and Hebble, and Huddersfield Broad canals.
Approximately two thirds of the original weir structure have failed in previous years since being replaced with other materials.
The principal structures to be constructed were a new 40m long reinforced concrete weir. This would replace the existing one. Also we would construct a Larinier fish pass and an elver pass.
The weir included a concrete crest with steel sheet piles up and downstream tying into a sloping concrete apron to the upstream and a stepped concrete apron to the downstream.
River Calder is fast-flowing river with a high flash flood risk.
Maintaining the flow of the river whilst constructing the new Weir and Fish Pass would require advanced programming and temporary works installation.
To comply with Environment Agency, it was also necessary to include a fish pass as part of the works.
For more information see the Canal and River Trusts article and waterways blog.
The Project would be split into three construction phases:
The scheme would be constructed through one of the wettest years in Huddersfield’s history. Several major floods to the river would occur causing some challenges.
The workforce persevered and overcame these challenges to complete the new weir and fish pass. As a result of this CPC Civils would receive appreciation and recognition from the Canal and River Trust.
Click here to add your own text
Ask a question